Warehouse digitalisation is often associated with robots, conveyors and automated storage. Monsoon’s latest productivity improvement points to a different opportunity: using operational data to redesign how people, equipment and time interact.
The fashion retailer has reduced unallocated time at its 250,000 sq ft distribution centre in Wellingborough to around 9%. The facility processes more than 15 million units annually for stores, e-commerce, marketplaces, concessions, wholesale and international customers. Its model combines automated sortation with manual picking in hanging, bulk and flat-floor areas.
Analytics exposed capacity hidden in the operating model
Monsoon implemented IMI’s warehouse labour productivity solution alongside an upgrade to its warehouse management system. The project began in one area before expanding across the site.
The first measurements found that unallocated activity represented 30–40% of warehouse time. The response was not simply to increase the pace of work. Monsoon used the evidence to investigate the design of its operation. Conveyors were moved so that the start and finish of an activity were positioned together. The analysis also showed that work was being distributed across a 24/7 operating pattern, leading the retailer to consolidate activity into Monday-to-Friday operations.
Unallocated time has since fallen to approximately 9%, converting between 21% and 31% of warehouse time into productive activity. This is a capacity gain achieved without a reported expansion of the facility or a requirement to add more automation equipment.
Industry 5.0 implications
The project also illustrates a people-centred approach to digital operations. Objective information gives managers a clearer basis for improving processes while allowing teams to test alternative ways of organising work. It shifts the conversation from individual effort to the conditions in which work is performed.
IMI remains involved as the site evolves. Consultants remeasure locations and reconfigure the system after layout changes, and Monsoon’s distribution-centre team can access IMI specialists directly.
The need for adaptability is ongoing. Changes in stockholding or buying patterns can alter the flow through the centre, creating new bottlenecks or periods of unused capacity. For industrial operators, the case suggests that resilience can be strengthened by combining automation with continuous measurement of labour, movement and schedule design.